Abbildungen der Seite
PDF
EPUB

Opinion of the Court.

previously let, it might be a question whether the contracts made by them for labor and materials would be binding as such upon the county." 115 Indiana, 243.

In Bartholomew Commissioners v. Jameson, 86 Indiana, 154, cited for the plaintiff, the assignment was of an entire sum due to the assignor for personal services. In Smith v. Flack, 95 Indiana, 116, likewise cited for the plaintiff, the municipality was not a party to the suit, nor were its rights or liabilities brought in question; but the controversy was upon the effect of an assignment as between the parties to it and persons claiming under them.

In the case at bar, by the original contract between Meyers & Son and the county commissioners, the contractors agreed to construct a jail for the county, and to provide all the materials therefor, for a gross sum of $20,000, which the commissioners agreed to pay, partly in monthly payments on their architect's certificate, and the rest upon the completion and acceptance of the building; and it was expressly agreed that the county should not in any manner be answerable or accountable for any materials used in the work; and also that, if the contractors should fail to finish the work by the time agreed on, they should pay to the commissioners, as and for liquidated damages, the sum of twenty-five dollars for every day the work should remain unfinished. Meyers & Son executed a bond for their faithful performance of the contract, as required by the statute.

By the subsequent assignment, to which neither the county nor the board of commissioners was a party, Meyers & Son undertook to assign to the plaintiff the obligation to construct and put in place in the jail all the iron work required by the original contract, as if the contract for such work had been awarded directly by the commissioners to the plaintiff; and undertook to fix the contract price for such work at $7700, to be paid by the commissioners at the times mentioned in the original contract.

The plaintiff in fact did the iron work according to the original contract and to the acceptance of the commissioners, and to the value of more than $7700, but not within the time

Opinion of the Court.

stipulated in that contract. Soon after the plaintiff began to do that work, the commissioners made a settlement with the original contractors, which, if valid, left in their hands much less than that sum.

The court declined to instruct the jury, as requested by the defendant, that the statutes of Indiana required contracts for the construction of jails and other county buildings to be advertised and let by the board of commissioners as an entirety, and not in parts; and that the contract between Meyers & Son and the board of commissioners was not divisible and assignable by the contractors, and their assignment of part of the contract to the plaintiff and mere notice thereof to the board did not impose any obligation upon the board to recognize the assignment, and to account and settle with and pay the plaintiff for work done and materials furnished by the latter.

There was conflicting evidence upon two points: 1st. Whether the commissioners before the settlement had notice of the assignment to the plaintiff; 2d. Whether the settlement was made in good faith. The judge instructed the jury that the plaintiff was entitled to recover, either if the defendant had such notice, or if the settlement was in bad faith. Exceptions were taken to the refusal to give the instruction requested, and to the instruction given upon the first alternative only. But it cannot be known on which alternative the jury proceeded in coming to their verdict. Upon the evidence before them and the instructions given, they may have concluded that the settlement between the defendant and the original contractors was in perfect good faith, and left in the defendant's hands much less than the sum claimed by the plaintiff, and that the defendant never assented to any assignment or division of the contract, and may have found for the plaintiff upon the single ground that they were satisfied that the defendant had notice of the assignment. The decision of the case therefore turns on the correctness of the instructions refused and given upon the effect of the assignment and notice.

This case does not require us to consider whether an assign

Opinion of the Court.

ment of the entire contract for the construction of the jail would have been consistent with the intention of the parties as apparent upon the face of the contract, or with the intention of the legislature as manifested by the statutes under which the contract was made. The plaintiff claims under no such assignment.

Those statutes and the judicial exposition of them by the Supreme Court of the State, as well as the terms of the contract itself, are quite inconsistent with the theory that the original contractors can, at their pleasure, and without the assent of the county commissioners, split up the contract and assign it in parts, so as to transfer to different persons or corporations the duty of furnishing different kinds of material and labor, and the right of recovering compensation for such material and labor from the county commissioners.

Both the statutes and the contract contemplate that the county commissioners shall be liable only to the contractors for the whole work, and not to any persons doing work or supplying materials under a subcontract with them.

The original contract of the county commissioners was for the construction by Meyers & Son of the building as a whole by a certain date; for the payment to them by the commissioners of a gross sum of $20,000 for such construction, upon an accounting with them from time to time; and for the payment by the contractors of twenty-five dollars, as liquidated damages, for every day that the building should remain unfinished beyond that date.

The assignment was not in the nature of a mere order for the payment of a sum of money; but it was of that part of the contract which related to the iron work, and required the assignee to perform this part of the work, and assumed to fix at the sum of $7700 the compensation for this part, which the assignee should receive from the commissioners. There is nothing, either in the original contract, or in the evidence introduced at the trial, to show what proportion the iron work bore to the rest of the work requisite for the construction and completion of the jail, or that any separate estimate of the cost or value of the iron work was contemplated by the

Opinion of the Court.

original contract, or ever made by the defendant, or by any officer or agent of the county.

In short, the only agreement which the county commissioners were proved to have made was with Meyers & Son, to pay them a gross sum of $20,000 for the whole work upon an accounting with them, and Meyers & Son paying damages as agreed for any delay in its completion. The agreement of Meyers & Son with the plaintiff assumed to compel the commissioners to pay the plaintiff, for its performance of part of the work, a definite sum of $7700, and made no provision for damages for delay, and thus undertook to fix a different measure of compensation from the original contract.

The facts that the iron work was done by the plaintiff to the acceptance of the commissioners, though after the time stipulated in the original contract, and was of the value of more than $7700, did not conclusively prove, as matter of law, that the commissioners, on behalf of the county, made or recognized any contract with or liability to the plaintiff, in the place and stead of its assignors and employers; or preclude the commissioners from insisting on the right to pay no more than the amount due, according to the original contract, for the whole of this and other work necessary to complete the building, and to ascertain the amount so due by an accounting and settlement with Meyers & Son, in which the sum due for all kinds of work, as well as the stipulated damages for any delay in completing the building, could be taken into consideration.

The county commissioners could not, without their consent, and at the mere election of the original contractors and their subcontractors and assignees, be compelled to account with the latter separately, or be charged with a separate obligation to pay either of them a part of the entire price, instead of accounting for and settling the whole matter with the original contractors.

It might be within the authority of the commissioners, upon becoming satisfied that Meyers & Son, after having performed a substantial part of their original contract, were unable to complete it, to give their consent to such an agreement with the plaintiff as was described in the assignment; and it is

Opinion of the Court.

possible that the jury would have been authorized upon the evidence to find such a consent.

But the difficulty with the instructions given to the jury is, that no question of such consent was submitted to or determined by them; and that they were in effect instructed, in direct opposition to the request of the defendant, that mere notice to the defendant of the assignment to the plaintiff would prevent the defendant from afterwards making a settlement with the original contractors in good faith and according to the sums justly due by the terms of the contract from either party to the other, without retaining in its hands enough to pay the plaintiff's claim. This instruction held the defendant bound by a contract to which it was not proved to have ever assented, and requires a new trial to be granted.

The cases in other States, cited for the plaintiff, in which municipal corporations have been held liable to an assignee of a contract, upon notice of the assignment, without proof of their consent, expressed or implied, are distinguishable from the case before us, and quite consistent with our conclusion.

In some of them, the assignments were of the whole or part of money already due, or to become due, to the contractor, in other words, assignments of a fund, and not of any obligation to perform work. Brackett v. Blake, 7 Met. 335; Field v. New York, 6 N. Y. 179; Hall v. Buffalo, 1 Keyes, 193; Parker v. Syracuse, 31 N. Y. 376; People v. Comptroller, 77 N. Y. 45. In others, the assignments were of entire contracts for the labor of convicts, or for work upon streets, which were held, from the nature of the subject, to imply no personal confidence in the contractor. Horner v. Wood, 23 N. Y. 350; Devlin v. New York, 63 N. Y. 8; Ernst v. Kunkle, 5 Ohio St. 520; St. Louis v. Clements, 42 Missouri, 69; Taylor v. Palmer, 31 California, 241.

The plaintiff much relied on a decision of the Supreme Court of Pennsylvania, in a case in which a contractor to build a school-house for a city assigned his right to all moneys due or to become due under it; the city, with notice of the assignment, and after the school-house had been built by the assignees and accepted and occupied by the city, paid the last

« ZurückWeiter »