Abbildungen der Seite
PDF
EPUB

Opinion of the Court.

taken by the United States in order that it might be protected from a double liability, in the event this court should hold that the Prairie Bank was entitled to any part of the fund.

Mr. Howard Henderson and Mr. A. B. Browne for Prairie State Bank. Mr. A. T. Britton was on their brief.

Mr. George A. King for Hitchcock. Mr. Rufus H. Thayer was on his brief.

Mr. Assistant Attorney General Dodge for the United States.

MR. JUSTICE WHITE, after stating the case, delivered the opinion of the court.

The question to be determined is which of the two contestants possesses a superior right to the fund. It is self-evident that, considering the agreements between Sundberg & Company and the bank as an intended transfer pro tanto of the rights of the latter to the results of the contract with the United States, such transfer would be void under § 3477, Rev. Stat. This position was not controverted in the discussion at bar, but it was asserted that as the bank had advanced money to complete the building and thus to enable Sundberg & Company to perform their contract obligations with the government, therefore the bank had an equitable lien 'upon the ten per cent retained by the government paramount to any lien in favor of Hitchcock, whose lien, it was contended, only arose from the date of his advances made to execute the contract upon Sundberg's default.

Thus the respective contentions are as follows: The Prairie Bank asserts an equitable lien in its favor, which it claims originated in February, 1890, and is therefore paramount to Hitchcock's lien, which it is asserted arose only at the date of his advances. The claim of Hitchcock, on the other hand, is that his equity arose at the time he entered into the contract of suretyship, and therefore his right is prior in date and paramount to that of the bank.

Opinion of the Court.

In considering these conflicting claims, it must be recognized at the outset that the terms of the original contract made by the United States with Sundberg were in nowise affected or changed by the agreements subsequently made between Sundberg and the Prairie Bank. Not to so consider would be admitting the application of section 3477 on the one hand, and then immediately proceeding to deny its effect on the other. We shall, therefore, in examining the rights of the parties proceed upon the hypothesis that the contract made by the United States remained in full force and effect, and that the rights, if any, of both parties to this controversy were subject to its terms.

That Hitchcock, as surety on the original contract, was entitled to assert the equitable doctrine of subrogation is elementary. That doctrine is derived from the civil law, and its requirements are, as stated in Etna Life Insurance Company v. Middleport, 124 U. S. 534: "1, that the person seeking its benefits must have paid a debt due to a third party before he can be substituted to that party's rights; and, 2, that in doing this he must not act as a mere volunteer, but on compulsion, to save himself from loss by reason of a superior lien or claim on the part of the person to whom he pays the debt, as in cases of sureties, prior mortgagees, etc. The right is never accorded in equity to one who is a mere volunteer in paying a debt of one person to another." See authorities reviewed at pages 548 et seq.

As said by Chancellor Johnson in Gadsden v. Brown, Speer's Eq. So. Car. 37, 41 (quoted and referred to approv ingly in the opinion in Insurance Co. v. Middleport, just referred to), "The doctrine of subrogation is a pure unmixed equity, having its foundation in the principles of natural justice, and from its very nature never could have been intended for the relief of those who were in any condition in which they were at liberty to elect whether they would or would not be bound; and, as far as I have been able to learn its history, it never has been so applied. If one with the perfect knowledge of the facts will part with his money, or bind himself by his contract in a sufficient consideration, any rule of

Opinion of the Court.

law which would restore him his money or absolve him from his contract would subvert the rules of social order. It has been directed in its application exclusively to the relief of those that were already bound who could not but choose to abide the penalty."

Under the principles thus governing subrogation, it is clear whilst Hitchcock was entitled to subrogation, the bank was not. The former in making his payments discharged an obligation due by Sundberg for the performance of which he, Hitchcock, was bound under the obligation of his suretyship. The bank, on the contrary, was a mere volunteer, who lent money to Sundberg on the faith of a presumed agreement and of supposed rights acquired thereunder. The sole question, therefore, is whether the equitable lien, which the bank claims it has, without reference to the question of its subrogation, is paramount to the right of subrogation which unquestionably exists in favor of Hitchcock. In other words, the rights of the parties depend upon whether Hitchcock's subrogation must be considered as arising from and relating back to the date of the original contract, or as taking its origin solely from the date of the advance by him.

A great deal of confusion has arisen in the case by treating Hitchcock as subrogated merely "in the rights of Sundberg & Co." in the fund, which, in effect, was saying that he was subrogated to no rights whatever. Hitchcock's right of subrogation, when it became capable of enforcement, was a right to resort to the securities and remedies which the creditor (the United States) was capable of asserting against its debtor Sundberg & Company, had the security not satisfied the obligation of the contractors, and one of such remedies was the right based upon the original contract to appropriate the ten per cent retained in its hands. If the United States had been compelled to complete the work, its right to forfeit the ten per cent and apply the accumulations in reduction of the damage sustained remained. The right of Hitchcock to subrogation, therefore, would clearly entitle him when, as surety, he fulfilled the obligation of Sundberg & Company, to the government, to be substituted to the rights which the United

Opinion of the Court.

States might have asserted against the fund. It would hardly be claimed that if the sureties had failed to avail themselves of the privilege of completing the work, they would not be entitled to a credit of the ten per cent reserved in reduction of the excess of cost to the government in completing the work beyond the sum actually paid to the contractor, irrespective of the source from which the contractor had obtained the material and labor which went into the building.

That a stipulation in a building contract for the retention, until the completion of the work, of a certain portion of the consideration, is as much for the indemnity of him who may be guarantor of the performance of the work as for him for whom the work is to be performed; that it raises an equity in the surety in the fund to be created; and that a disregard of such stipulation by the voluntary act of the creditor operates to release the sureties, is amply sustained by authority. Thus in Calvert v. London Dock Co., 2 Keen, 638, (1838,) where a contractor had undertaken to perform certain work, and it was agreed that three fourths of the work, as finished, should be paid for every two months, and the remaining one fourth upon the completion of the whole work, it was held that the sureties for the due performance of the contract were released from their liability by reason of payments exceeding three fourths of the work done having been made to the contractor without the consent of the sureties before the completion of the whole work. To the argument that the extra advances really went into the work and so enured to the benefit of the sureties, Lord Langdale, Master of the Rolls, answered as follows (p. 644):

"The argument, however, that the advances beyond the stipulations of the contract were calculated to be beneficial to the sureties, can be of no avail. In almost every case where the surety has been released, either in consequence of time being given to the principal debtor, or of a compromise being made with him, it has been contended that what was done. was beneficial to the surety-and the answer has always been, that the surety himself was the proper judge of thatand that no arrangement, different from that contained in his

Opinion of the Court.

contract, is to be forced upon him; and bearing in mind that the surety, if he pays the debt, ought to have the benefit of all the securities possessed by the creditor, the question always is, whether what has been done lessens that security.

"In this case, the company were to pay for three fourths of the work done every two months; the remaining one fourth was to remain unpaid for, till the whole was completed; and the effect of this stipulation was, at the same time, to urge Streather to perform the work, and to leave in the hands of the company a fund wherewith to complete work, if he did not; and thus it materially tended to protect the sureties.

"What the company did was perhaps calculated to make it easier for Streather to complete the work, if he acted with prudence and good faith; but it also took away that particular sort of pressure which by the contract was intended to be applied to him. And the company, instead of keeping themselves in the situation of debtors, having in their hands one fourth of the value of the work done, became creditors to a large amount, without any security; and, under the circumstances, I think that their situation with respect to Streather was so far altered that the sureties must be considered to be discharged from their suretyship."

In General Steam Navigation Co. v. Rolt, 6 C. B. (N. S.) 550, (1859,) upon a second appeal of the case, the Exchequer Chamber held that a plea by a surety to an action to recover from him the excess of cost in completing a ship after the contractor had made default, and also a stipulated sum by way of damages for delay, to the effect that the owner, without the consent of the surety, had allowed the builder to anticipate a greater portion of the last two instalments specified in the contract, and thus materially and prejudicially alter the surety's position, was a prima facie answer to the action, and that the onus lay upon the plaintiffs to prove the allegations of their reply that the advances were made with the knowledge and assent and at the request of the surety. It was argued on behalf of the plaintiffs, among other contentions, that under the circumstances in the case there was nothing to show that the defendant could be prejudiced in

« ZurückWeiter »